Notes: Bishop School Construction Update
Earlier this month I attended a meeting at Bishop School in which Rob Smiley, COO of Sunnyvale School District, brought us up to speed on the current construction plans. I took noted and shared on Nextdoor.com, and I’m sharing them here for better community access.
Construction Update
Maps viewable in school office, and online at: http://www.sesd.org/Page/3722
… re-bidding is not yet complete …
October — Temp Classrooms to be installed on blacktop (note: these were installed last week)
December — Fencing / Construction begins (North Side)
August 2017 — move into new rooms
August 2018 — project complete
Roughly:
North Side construction thru Aug 2017
South Side construction thru Aug 2018
Construction Expectations:
– Reduced on-street parking (25 parking spaces removed)
– Increased traffic
– Reduced play area
– “Hard Hat Cafe” (during kitchen construction, from June 2017)
– Noise (no loud construction during testing)
– Demolition (.. asbestos .. “abatement” ..)
Q: When does Maude Ave bike lane (remove parking) happen?
A: Do not know